CONSTRUCTION CONTRACT…
THIS CONSTRUCTION CONTRACT (the “Contract”) is made and entered into on [Date], by and between:…
Contractor: [Legal Name and Address of Contractor]…
(collectively referred to as the “Parties”).…
1. PROJECT DESCRIPTION:…
1.1 Scope of Work:…
The Contractor agrees to perform the construction work described in Exhibit A attached hereto (the “Work”). 2. CONTRACT PRICE:…
2.1 Total Contract Price:…
The total agreed-upon contract price for the comprehensive completion of the entire project, inclusive of all labor, materials, equipment, overhead, profit, taxes, and other associated costs, is set at [Amount] (“Lump Sum Price”).…
The Lump Sum Price covers all work, services, and deliverables detailed in the Construction Agreement, forming the complete scope of the project as mutually agreed upon by the Owner and the Contractor.…
Payments shall be disbursed to the Contractor in accordance with the predetermined payment schedule as outlined in the Construction Agreement. The Owner shall make payments to the Contractor within [number of days] days of the Contractor’s submission of a properly invoiced request for payment.…
3. TIMELINE:…
3.1 Project Schedule:…
The Work shall be completed within [Specify the number of days/weeks/months] from the commencement date, unless otherwise extended by mutual agreement.…
4. CHANGE ORDERS:…
4.1 Changes to Scope:…
Any changes to the scope of the Work must be agreed upon in writing by both Parties.…
4.2 Adjustments to Price and Schedule:…
Changes to the scope of work may result in adjustments to the contract price and project schedule.…
5. WARRANTIES:…
5.1 Workmanship Warranty:…
The Contractor warrants that all work performed shall be of good quality and free from defects for a period of [Specify warranty period] from the date of completion. 6. INSURANCE:…
The Contractor agrees to maintain appropriate insurance coverage, including liability and worker’s compensation insurance, throughout the duration of the project.…
7. PERMITS AND REGULATIONS:…
7.1 Permits:…
The Contractor shall obtain all necessary permits and approvals for the Work.…
7.2 Compliance:…
The Work shall comply with all applicable laws, regulations, and building codes.…
8. TERMINATION:…
8.1 Termination for Convenience:…
The Client may terminate the Contract for convenience upon written notice to the Contractor, subject to payment for work performed up to the date of termination.…
8.2 Termination for Cause:…
Either Party may terminate the Contract for cause upon written notice if the other Party breaches any material term or condition herein and fails to cure such breach within [Specify cure period] days.…
9. FORCE MAJEURE…
“Force Majeure” means the occurrence of an event or circumstance that prevents or impedes a party from performing one or more of its contractual obligations under the contract, if and to the extent that that party proves:…
[a] that such impediment is beyond its reasonable control; and…
[b] that it could not reasonably have been foreseen at the time of the conclusion of the contract; and…
[c] that the effects of the impediment could not reasonably have been avoided or overcome by the affected party.…
In the absence of proof to the contrary, the following events affecting a party shall be presumed to fulfil conditions (a) and (b) under paragraph 1 of this Clause: (i) war (whether declared or not), hostilities, invasion, act of foreign enemies, extensive military mobilisation;…
(ii) civil war, riot, rebellion and revolution, military or usurped power, insurrection, act of terrorism, sabotage or piracy;…
(iii) currency and trade restriction, embargo, sanction;…
(iv) act of authority whether lawful or unlawful, compliance with any law or governmental order, expropriation, seizure of works, requisition, nationalisation;…
(v) plague, epidemic, natural disaster or extreme natural event;…
(vi) explosion, fire, destruction of equipment, prolonged break-down of transport, telecommunication, information system or energy;…
(vii) general labour disturbance such as boycott, strike and lock-out, go-slow, occupation of factories and premises.…